Road work on the Radio Road interchange, which will completed in August 2014, continues this week with multiples projects. The project website, www.dot.wisconsin.gov/projects/nwregion/wis35radioroad/, says that this week's projects include: Box culvert structure excavation; the stripping of topsoil for Paulson Road; clearing and grubbing for Paulson Road, Radio Road and southeast ramp; and the placing of utility casing pipes for Radio Road.